Hong Kong's New Form of Building Contract : 20 Issues to be Aware Of
General Matters
- A new and overriding duty on the parties to act "reasonably and expeditiously" when administering the contract.
- Provisions aimed at curtailing multi-tiered sub-contracting.
- A requirement for bonds from both the main contractor and nominated sub-contractors.
Programming/Extensions of Time
- Enhanced provisions dealing with the production and use of a Master Programme.
- Interest payable upon the refunding of liquidated damages.
- A significant increase in the grounds for granting extensions of time.
Variations
- Express power to issue Variations up to date of the Defects Rectification Certificate.
- Variations are now defined as either changes to the work ill the manner in which it is executed.
- Contractor has a reasonable right to object to variations concerning the manner in which the work is undertaken.
- Contractor can question the power of the Architect and also seek clarification of whether an instruction is a Variation.
- Valuation rules now restrict changes to "conditions" as physical and not financial.
- Variations can now factor in the effect of a substantial change in quantity although the Contract does not state what aspects of the rate can be altered.
- The three traditional "rules" of valuation are narrowly defined. There is no longer a test of reasonableness regarding whether or not the rates can be used. The quantity surveyor is obliged only to consider physical circumstances of character, conditions and quantity of work.
- The Contract refers to valuation by "fair rates" and also a "fair valuation", suggesting there is a distinction. It may be the case that fair rates can be derived from the Contract Bills whereas a fair valuation can be from extrinsic means.
- The consequential effect of a Variation on other work can now be valued.
Loss and Expense
- Loss and expense (and disturbance) arising from variations is expressly excluded from the "value" of Variations; now a "cost" item.
- Loss and expense qualifying events are substantially increased.
- The definition of loss and expense does not state whether or not it includes profit.
- Strict notice and reporting requirements for claims for additional payment. Failure to comply with either may result in claim being waived.
- All claims for extra payment are to be resolved quickly, generally within 60 days of notifying.
Heller Ehrman
September 2005