Those who are engaged in international project contracting will no doubt be familiar with the FIDIC forms of contracts and the requirement therein for disputes to be referred to a Dispute Adjudication Board ("DAB") for its decision in the first instance. One of the potentially difficult issues in this area relates to the enforcement of a DAB decision by means of arbitration. Many have found this issue problematic and it would appear to us that a large part of the problem may be due to the fact that the wording and significance of the relevant FIDIC provisions are not always fully understood. In the recent decision of PT Perusahaan Gas Negara (Persero) TBK v. CRW Joint Operation [2010] SGHC 202 ("PGN case"), the Singapore High Court had the opportunity to consider this issue.
Under a contract which was based upon the FIDIC Conditions of Contract for Construction (1st Edition, 1999) ("1999 Red Book") but with modifications, PT Perusahaan Gas Negara (Persero) TBK ("PGN") engaged CRW Joint Operation ("CRW") to design, procure, install, test and pre-commission a pipeline and an optical fibre cable in Indonesia ("Contract"). While the Contract was being performed, a dispute arose between the parties over certain variation order proposals and requests for payments submitted by CRW.
Pursuant to Clause 20.4 the parties referred the dispute to a DAB which had been appointed. The DAB heard the dispute and made several decisions, all of which were accepted, save for one which required PGN to pay CRW the sum of US$17,298,834.57. In accordance with the Contract, PGN submitted a Notice of Dissatisfaction ("NOD") in respect of that decision. The matter remained unresolved and CRW subsequently brought an arbitration against PGN in an attempt to enforce the DAB decision. Following a hearing which was conducted before an arbitral tribunal comprising three arbitrators, a majority final award was rendered holding that the DAB decision in question was binding and that PGN had an obligation to make immediate payment for the sum of US$17,298,834.57 to CRW.
CRW subsequently took out an application before the High Court of Singapore to register the award as a judgment in Singapore. In response, PGN applied to Court to set aside the registration order. PGN also applied to Court to set aside the arbitral award pursuant to Section 24 of the Singapore International Arbitration Act and Article 34(2) of the UNCITRAL Model Law.
The Court found in favour of PGN and set aside the award which had been obtained by CRW under Article 34(2)(a)(iii) of the UNCITRAL Model Law.
In reaching its decision, the Court discussed the fundamental distinction between an arbitration contemplated under Clause 20.6 and one contemplated under Clause 20.7, as follows:
The Court held that:
The PGN case provides a timely reminder of the fundamental yet often overlooked distinction between Clause 20.6 and Clause 20.7. Whether a DAB decision should be enforced by means of arbitration under Clause 20.6 or Clause 20.7 will depend entirely on whether a valid NOD had been submitted and consequently, whether the DAB decision is "final and binding" (no NOD submitted) or merely "binding" (valid NOD submitted).
To summarise the position, a DAB decision may be enforced by means of arbitration under a FIDIC contract in one of two ways:
As can be seen from the PGN case, it is critical to ensure that the DAB decision is enforced by arbitration under the correct provision, so that the eventual award will be less susceptible to being challenged by the unsuccessful party and set aside by the Court.
For drafting purposes, it should be noted that the wording of Clause 20.7 of the 1999 Red Book (specifically the term "final and binding") has been retained in both the FIDIC Multilateral Development Bank Harmonised Edition forms published in 2005 (as amended in 2006) and 2010. To avoid the problem posed by "final and binding" requirement, the wording of Clause 20.7 (or the corresponding provisions) could be amended so as to exclude the "final and binding" requirement altogether. One way to do this would be adopt the wording used under the FIDIC Conditions of Contract for Design, Build and Operate Projects (1st Edition, 2008) ("the Gold Book"), which provides as follows:
"In the event that a Party fails to comply with any decision of the DAB, whether binding or final and binding, then the other Party may, without prejudice to any other rights which it may have, refer the failure itself to arbitration under [Clause 20.8] for summary or other expedited relief, as may be appropriate."
Finally, and as mentioned above, even if the "final and binding" requirement has been retained, it remains open for the successful party to rely upon Clause 20.6 to obtain an interim or provisional award, pending a final determination of the dispute at large. CRW did not pursue this option in the PGN case, but this is an approach that can potentially be adopted to overcome the "final and binding" requirement imposed by the wording of Clause 20.7.
Hogan Lovells Lee & Lee Singapore, Talking Point: Engineering and Construction - Asia
Paul Teo, Consultant
November 2010